The third phase of a Rochester program to replace pavement on several local streets starts Wednesday, with milling to be finished by Thursday, and paving scheduled for the following week.
This is the order of streets to be completed:
• Ninth Street Southeast between Broadway and Third Avenue;
• Fifth Street Northeast between Ninth and 11th avenues;
• Seventh Street Northeast between 11th and 14th avenues;
ADVERTISEMENT
• Fifth Avenue Northeast between 20th Street and Northern Heights Drive, including the Fifth Avenue cul-de-sac;
• 15th Avenue Northeast between Fourth and Fifth streets;
• 17th Avenue Northeast between Third and Fifth streets.